truman ave reconstruction

Truman Ave Reconstruction and Kennedy Road Water Main Improvements

Location: Richland, WA

Date: August 2024

Details:

This project includes the installation of approximately 4500 LF of 12-inch ductile iron watermain, this will include saw cutting and repairing the existing asphalt roadway by means of patching, and the reconstruction of 0.1 miles of a new roadway of Truman Avenue. The work involves the construction of the roadway, embankment and compaction, crushed surfacing top and base course, HMA ½”, curb, gutter, and sidewalk for the east side of the street, street light conduit and illumination.